What Law 7-81 Actually Permits Regarding Expropriation in Morocco

definition of public purpose in Morocco
Public purpose means a legally declared collective need that may justify the compulsory acquisition of immovable property in exchange for compensation.
property subject to expropriation under Law 7-81
Land, buildings and rights in rem over immovable property may be expropriated, whether registered or unregistered.
definition of expropriating authority in Morocco
The expropriating authority is the public entity, or legally authorised person, pursuing the acquisition of the property for the project declared to be for a public purpose.
grounds for expropriation in Morocco
Roads, transport, schools, hospitals, urban facilities and public works are among the projects that may justify expropriation.
rights in rem and expropriation
Usufruct, certain rights of enjoyment and other rights in rem over the immovable property must be identified and, depending on their nature, compensated.

Expropriation for public purposes in Morocco allows a public entity to compulsorily acquire immovable property needed for a project recognised as serving a public purpose, in exchange for fair compensation. Its principal legislation is Law No. 7-81, promulgated by Dahir No. 1-81-254 of 6 May 1982 and supplemented by Decree No. 2-82-382 of 16 April 1983. In practical terms, an administrative authority cannot take land by means of a simple letter or by orally invoking a road project: it must comply with the instruments, publicity requirements and judicial procedure prescribed by this law.

A public purpose may involve a road, railway, school or hospital facility, hydraulic structure, sanitation project, urban development or sports infrastructure. The concept remains broad, but it is not beyond scrutiny. The Administrative Court may review the authority of the person issuing the instrument, the genuine public nature of the objective and the formalities imposed by Articles 5 to 10 of Law 7-81. A primarily private project artificially presented as public may therefore be challenged through an action for annulment.

Built or undeveloped immovable property and rights in rem over immovable property may be concerned. This includes an apartment, commercial building, agricultural land, unregistered plot, usufruct or certain rights attached to the property. Movable property is not expropriated under this regime. Property already forming part of the public domain does not follow the same framework, because it is governed by the rules on allocation and transfer between public entities rather than by conventional expropriation.

The expropriating authority may be the State, a territorial authority, a public institution or another person authorised to carry out a public-purpose operation. This expropriating authority must be distinguished from the project owner, the concession holder and the contractor responsible for the works. In practice, this distinction is essential to determine to whom a claim should be addressed, who must deposit the compensation and which instrument should be challenged. The name of the expropriating authority normally appears in the declaration of public purpose and in the court applications.

Step 1 — Declaration of Public Purpose and Transferability Order

publication of public-purpose decree in Morocco
The declaration of public purpose must be published in the Official Gazette and be subject to local publicity formalities.
public inquiry for expropriation in Morocco
The administrative inquiry provided for in Article 6 of Law 7-81 lasts two months and allows interested parties to inspect the file and submit their observations.
transferability order in Morocco
The transferability order identifies the plots and rights in immovable property whose acquisition is necessary for the project.
time limit for transferability order
The property must be designated within the statutory time limit, and the transferability order permits referral to the court for only two years.
Official Gazette expropriation
Consulting the Official Gazette makes it possible to verify the date, author and content of the declaration of public purpose.

The procedure begins with a declaration of public purpose issued in the regulatory form applicable to the project. This instrument is published in the Official Gazette and is subject to the local publicity measures prescribed by Law 7-81 and its implementing decree. The file is lodged with the relevant administrative departments so that interested parties may inspect the plan and submit their observations. Article 6 provides, in particular, for an administrative inquiry lasting two months. Inconspicuous or incomplete posting does not replace the statutory formalities.

The declaration of public purpose may define a general area without immediately identifying each plot. A transferability order is then issued to identify precisely the immovable properties required for the project. Under Article 7 of Law 7-81, this designation must take place within two years following publication of the declaration where the properties have not already been identified. The transferability order is itself subject to publicity requirements. Contrary to information sometimes repeated online, Moroccan law does not provide for the declaration to have a general ten-year period of validity comparable to certain foreign regimes.

The transferability order must make it possible to identify the plots, their land-registration references and the persons who may hold rights in them. Its validity for commencing the judicial phase is limited to two years by Article 9 of Law 7-81. If the expropriating authority does not refer the matter to the court within this period, expropriation can normally no longer be ordered on the basis of that expired instrument. A new administrative procedure then becomes necessary. Verifying the publication dates should therefore be one of the first steps taken.

During the inquiry, the owner should submit written observations and retain a receipt. The owner may report an error in the surface area, an incorrect cadastral reference, or the existence of a house, lease, plantations or commercial activity. For registered property, the status should be checked with the ANCFCC. For unregistered melk property, adoul deeds, administrative certificates and succession documents must be gathered. Some owners discover the project at a late stage; however, lawful publication may start an appeal period running even if no letter was received at their home address.

Lawyers at your service

Real Estate Law lawyers in Morocco

Verified profiles, members of Moroccan bar associations — call or message them directly from their page

Hatim ELKHATIB
29 years of experience

Hatim ELKHATIB

Cabinet Me. Hatim ELKHATIB•Tangier

Lawyer registered with the Tangier Bar since 1997, practising exclusively in business law, both in advisory work and in litigation. We have proven experience in advising and representing national and international companies. Our professionals work in Arabic as well as in French, English and Spanish.

Business LawReal Estate LawIntellectual Property+2
French · Arabic · English · +1
Direct contact only
Mohammed TAMOURO
6 years of experience

Mohammed TAMOURO

Cabinet Me. Mohammed TAMOURO•Casablanca

A lawyer registered with the Casablanca Bar since 2020 and an international arbitrator, I specialise in Business Law. My firm ‘LPF Counsel’ assists individuals in their litigation and provides advice to multinationals and Moroccan companies as a Business Partner.

Business LawReal Estate LawImmigration Law+33
French · Arabic · English · +1
Direct contact only
Jamal EL HASNAOUY
11 years of experience

Jamal EL HASNAOUY

Cabinet Me. Jamal EL HASNAOUY•Casablanca

A lawyer at the Casablanca Bar, I assist companies and individuals in advisory work and litigation, particularly in business law, intellectual property, contract law and arbitration. My aim is to provide effective, tailored legal support geared towards protecting my clients' interests.

Business LawIntellectual PropertyReal Estate Law+14
French · Arabic · Amazigh (Berber) · +1
Direct contact only

Step 2 — Transfer of Ownership Before the Administrative Court

Administrative Court expropriation Morocco
The Administrative Court for the place where the immovable property is located rules on the transfer of ownership and compensation.
expropriation judgment in Morocco
The judgment transfers the property to the expropriating authority and determines the compensation payable to the holders of recognised rights.
taking possession following expropriation
Early possession requires a judicial decision and the payment or deposit of provisional compensation.
depositing compensation with CDG
A deposit with CDG secures the compensation when its beneficiary cannot yet be paid directly.
works before compensation
Works commenced without apparent legal authority must be documented immediately to preserve evidence and remedies.

If no amicable acquisition is reached, the expropriating authority refers the matter to the Administrative Court within whose jurisdiction the immovable property is located. Article 8 of Law No. 41-90 establishing the Administrative Courts grants them jurisdiction over disputes related to expropriation for public purposes. The court application must be accompanied by the administrative instruments, evidence of publicity, plans and information identifying the property. The court reviews compliance with the formalities governing the transfer. It is therefore not sufficient for the administrative authority merely to assert that the project is urgent.

Law 7-81 distinguishes between the transfer of ownership and taking possession. The expropriation judgment legally transfers the immovable property and determines the compensation, whereas possession may be authorised earlier by an order, subject to the payment or deposit of provisional compensation. Articles 18 to 23 govern this judicial phase. In practice, both applications are frequently filed together, but they do not have the same effects and are not necessarily challenged through the same remedies.

Possession must not be taken without a financial guarantee. Where the owner is known and the owner's right has been established, the provisional compensation may be paid to that owner. Where there is an unsettled succession, disputed co-ownership, a mortgage or a dispute over ownership, the amount is generally deposited with the Caisse de Dépôt et de Gestion (CDG). Depositing the amount does not mean that the owner accepts it. It allows the expropriating authority to proceed while preserving the dispute over the final compensation.

Particular care is required where works begin before the procedure has been completed. The condition of the premises must immediately be formally recorded by a judicial officer, dated photographs must be collected, and the references of the order authorising possession must be requested. Physical occupation without lawful authority may incur the liability of the public entity, but the appropriate strategy depends on the nature of the defect and the stage reached in the procedure. The owner should neither physically obstruct the works nor sign under pressure any official record presented as a mere formality.

How Expropriation Compensation Is Calculated in Morocco

calculation of expropriation compensation in Morocco
Compensation covers actual, certain and direct loss in accordance with the criteria established by Article 24 of Law 7-81.
market value of expropriated land
The value of the land depends in particular on comparable sales, zoning, access, utilities and its actual development potential.
valuation date for expropriation compensation
The value is assessed as at the date of transfer, while being limited by the property's value on the date of publication of the instrument designating the properties.
increase in value from public project
Any increase in price directly created by the project giving rise to the expropriation is excluded from the compensation.
court-appointed expert appraisal in expropriation
The court-appointed expert proposes a valuation following adversarial proceedings, but the court retains the power to determine the final amount.
compensation for business assets
Commercial loss must be established through a lease, accounting records, tax returns and evidence demonstrating direct loss.

The calculation rules are set out primarily in Article 24 of Law 7-81, and not in Article 36 as some summaries indicate. Compensation covers only actual and certain loss directly caused by the expropriation. The value is assessed as at the date of the decision ordering the transfer, but is capped at the value held by the property on the date of publication of the transferability order or of the declaration directly designating the properties. Speculative improvements made after publication may be disregarded.

The court determines the property's actual value based on its location, surface area, use, planning status, access, utilities and comparable transactions. Land classified as agricultural is not automatically valued as development land, even if buildings exist nearby. Conversely, the administrative authority cannot apply an agricultural price if the planning documents and objective characteristics establish that the land had development potential before the project. The zoning applicable on the reference date must be submitted in the case file.

Any increase in value created by the announcement of the public project is disregarded. For example, the owner of a plot near a future railway station cannot claim the increase in value arising solely from that station. Likewise, any artificial decrease caused by the same project must not be held against the owner. This rule prevents the administrative authority from benefiting from a depreciation it created itself. A chronological analysis of comparable sales is therefore crucial: transactions occurring too long after the project was announced may be less relevant.

Separate losses may be added to the value of the land and buildings where they are proven. They may include the loss of crops, plantations, the relocation of equipment, the interruption of a business operation, the loss in value of a remaining parcel or the rights of an occupant holding an enforceable title. Business assets are not compensated solely on the basis of an oral statement: balance sheets, tax returns, the commercial lease, authorisations and previous turnover must demonstrate the existence and extent of the loss.

The court may order an adversarial real-estate appraisal. The expert inspects the property, examines the title documents and proposes a value; the expert does not deliver the judgment. The owner must provide the expert with a comparison file containing recent sales, their land-registration references, the development plan and the physical characteristics of the land. If the report overlooks decisive factors, written observations may be filed and a supplementary appraisal or counter-appraisal may be requested. The court remains free to adopt or reject the expert's technical findings.

Amicable compensation offer: negotiate, accept or refuse

amicable expropriation offer Morocco
An amicable offer is a negotiable proposal that the owner may accept, refuse or discuss by providing supporting evidence.
refusal of expropriation compensation
Written refusal of the offer does not extinguish the right to compensation and allows the court to determine the amount in the event of disagreement.
expropriation counteroffer
A credible counteroffer must state a specific amount and be supported by comparable sales and evidence of the alleged losses.
deadline to respond to expropriation offer
Article 10 does not establish a general thirty-day deadline applicable to every offer, so the notice and procedure must be examined.
amicable expropriation agreement
The agreement must identify the rights transferred, the compensation included and the payment terms before any final release is signed.

Before or during the judicial phase, the expropriating authority may propose an amicable acquisition based on an administrative valuation. The owner may request the valuation report, the exact plan of the land take and a breakdown covering the land, buildings, plantations and other losses. Contrary to the claims made in some practical guides, Article 10 of Law 7-81 does not establish a general thirty-day deadline for accepting every amicable offer. The notice received must be read and the specific deadline stated in it must be checked, along with the actual status of the proceedings.

Refusing the offer does not result in the loss of the right to compensation. The disagreement will normally lead the administrative court to determine the amount, often following an expert assessment. The response must be in writing, dated and sent by a method that provides proof of receipt. It may include a quantified counterproposal supported by a private expert report, comparable sales and evidence of consequential losses. A purely emotional response, with no alternative valuation or documentation, rarely assists negotiations.

Acceptance requires a precise understanding of what is being settled. The agreement must identify the property, its area, the holders of rights, the amount and the payment schedule. It is necessary to check whether the amount covers only the ownership interest or also relocation, plantations, the commercial lease and loss of business. Once definitively formalised, an amicable transfer is difficult to challenge, except on the grounds of defective consent or a serious irregularity. A general release should therefore not be signed before the payment and its effects have been verified.

Negotiations are more effective when the valuation is based on verifiable references. A property listing proves only an asking price, not a price actually paid. Comparable deeds of sale, available tax data, land registry information and reasoned expert assessments are more reliable. Similar properties must also be compared: the same neighbourhood, the same zoning, the same access and a period close to the legally relevant date. Registered land with utility services is not comparable to disputed or landlocked land located several kilometres away.

Challenging expropriation in Morocco: remedies and deadlines

expropriation proceedings before administrative court
The administrative court has jurisdiction over both legality disputes and the determination of compensation, through separate claims.
deadline to challenge public utility decree
An application for annulment on grounds of misuse of authority must, in principle, be filed within sixty days following publication or notification of the act.
challenging expropriation compensation
Challenging the amount requires a reasoned valuation, comparable transactions and proof of each loss claimed.
appeal against expropriation judgment
An appeal concerning compensation falls within the jurisdiction of the competent administrative court of appeal under the remedies provided by law.
procedural defect in expropriation
Defective publication, lack of authority by the issuer or expiry of the transferability order may support a challenge to legality.
retransfer of expropriated property
Article 43 permits, subject to its conditions, a request for the return of property that has not been used for the stated public utility purpose.

Two types of proceedings must be distinguished. An application for annulment challenges the legality of an administrative act, such as a declaration of public utility issued by an authority lacking jurisdiction, defective publication or misuse of powers. Compensation proceedings concern the value of the property and the losses caused by the transfer. Requesting higher compensation does not automatically lead to the cancellation of the project. Conversely, raising an irregularity in submissions concerning an expert assessment does not replace an application for annulment filed within the applicable time limit.

Under Article 23 of Law No. 41-90, an application for annulment on grounds of misuse of authority must, in principle, be filed within sixty days following publication or notification of the administrative decision. The starting date may be open to discussion where the owner has received no individual notice, but it would be dangerous to wait. A prior administrative appeal may affect the deadline if it is properly filed. Its impact must be verified on a case-by-case basis rather than assumed.

To challenge the compensation, the owner must appear in the expropriation proceedings, submit evidence of title and request an inter partes valuation. A judgment determining compensation may be challenged through the remedies provided by Law 7-81 and the rules of administrative procedure. The appeal is brought before the competent administrative court of appeal established by Law No. 80-03. The available remedies against the transfer itself and against the possession order are more limited; the decision received must be identified precisely before any action is taken.

A properly prepared application includes the land title or deeds of ownership, a recent certificate of ownership, the published acts, notices, parcel plan, planning documents and a reasoned valuation. For a business activity, the lease, commercial register, tax returns and accounts must also be provided. The application is filed with the registry of the competent administrative court, and representation by a lawyer is, in contentious practice, the rule that should be observed. A sworn translation may be required for foreign documents belonging to a Moroccan residing abroad.

Retransfer is a separate remedy. Article 43 of Law 7-81 allows former owners or their successors in title to request the return of property where it has not been used for the stated purpose under the conditions and within the time limits prescribed by law. This action requires an examination of the transfer date, the actual use and any authorised changes to the project. It generally entails repayment of the compensation in accordance with the terms determined by law or by the court. Legal advice should be sought without waiting several years after discovering that the project has been abandoned.

Special cases: co-ownership, tenants and partial expropriation

expropriation of jointly owned property in Morocco
Joint ownership does not prevent expropriation, but each heir must prove their share in order to receive compensation.
tenant compensation for expropriation
A tenant may claim compensation for their own loss if they prove their lease, occupancy and the losses directly caused.
remainder after partial expropriation
Any loss of access, development potential or economic usefulness of the remaining land must be valued separately.
expropriation of agricultural land
The soil, trees, irrigation systems, buildings and crops are separate valuation components.
temporary occupation in Morocco
Temporary occupation authorises limited use without a transfer of ownership and gives rise to a right to compensation for proven damage.
expropriation involving a Moroccan abroad
A Moroccan residing abroad may act through an authorised representative under a compliant power of attorney and must promptly regularise inheritance or land registry documents.

Jointly owned property may be expropriated even if all the heirs do not agree. Each co-owner must, however, be able to have their entitlement to the compensation recognised. Where the estate has not been distributed or an heir lives abroad, direct payment is often blocked and the amount is deposited. The deed of inheritance, powers of attorney, identity documents and, where applicable, deeds of partition must be assembled. A power of attorney executed abroad must comply with the applicable legalisation, apostille or consular form requirements.

A tenant does not own the land, but may suffer a separate loss. An enforceable commercial lease, a declared business and financial statements may support a claim relating to the loss of business assets, relocation or interruption of operations. A residential tenant may claim directly established losses caused by the eviction, without receiving the value of the property. The lease, receipts, condition report and proof of occupancy must be declared at an early stage; otherwise, the expropriating authority may deal only with the registered owner.

In the event of partial expropriation, the dispute is not limited to the number of square metres taken. The remainder may lose its access, become too small for construction, have an unusable shape or no longer support profitable agricultural operations. The provisions of Law 7-81 concerning partial land takes allow for consideration of the acquisition of the remainder or compensation for its loss in value, depending on the circumstances. A plan prepared by a land surveyor is often more persuasive than a mere assertion that the remaining plot is unusable.

For agricultural land, the valuation must distinguish between the soil, plantations, irrigation facilities, farm buildings and lost crops. Claimed yields must be proved by invoices, declarations, sales contracts or agronomic reports. Collective, habous or guich status may profoundly alter the identification of rights holders and the applicable procedure. Such land should not automatically be treated as ordinary melk property. The opinion of the competent authorities may be required even before the amount is discussed.

Temporary occupation, governed by Articles 50 et seq. of Law 7-81, does not transfer ownership. It permits, in particular, surveys, the storage of materials, access to the construction site or works limited in time. It must be based on a valid legal instrument and give rise to compensation for damage caused. In the context of major infrastructure projects being prepared for the 2030 deadlines, political or technical urgency does not remove the requirements of deposit, compensation or judicial review. The owner must request a copy of the exact instrument being relied upon.

Documents, costs, timelines and mistakes to avoid in 2026

expropriation documents in Morocco
Ownership documents, land certificates, plans, notices and evidence of value form the foundation of the case file.
court-appointed property expert fees
In practice, the advance often ranges from 5,000 to 30,000 dirhams in 2025-2026, subject to the amount set by the court.
expropriation lawyer’s fees
A complete first-instance case often costs between 10,000 and 50,000 dirhams, with no mandatory national fee scale.
expropriation proceedings timeline in Morocco
A compensation dispute may take twelve to thirty-six months at first instance and longer in the event of an appeal.
ANCFCC land title and expropriation
The ANCFCC certificate of ownership identifies the registered owner, encumbrances and rights affecting registered property.
expropriation lawyer in Morocco
The lawyer distinguishes between remedies, monitors deadlines and converts the owner’s valuation into a legally substantiated claim.

The minimum case file includes a copy of the identity card, the land title or melk deeds, a recent certificate of ownership, the cadastral plan, inheritance documents and the notices received. Building permits, plans, work invoices, leases, photographs and evidence of economic use must be added. To quantify the value, gather comparable sales references, the development plan and a valuation report. An incomplete file may result in the amount remaining on deposit for a prolonged period even when the amount of compensation is no longer disputed.

There is no mandatory national fee scale for lawyers or private experts. In practice in 2025-2026, a court-ordered property valuation may require an advance of approximately 5,000 to 30,000 dirhams, depending on the area, number of plots and complexity; the amount is set by the court. Lawyers’ fees for a complete first-instance case are often between 10,000 and 50,000 dirhams, excluding appeals, expert assessments and taxes, depending on the stakes involved. These ranges are based on professional practice, not an official fee scale.

Court registry fees and costs are assessed according to the nature of the claim, Law No. 23-86 concerning legal costs and the financial legislation in force. It would be imprudent to state that there is a universal stamp duty of 200 or 500 dirhams for every administrative action. The court registry and lawyer must prepare an up-to-date statement before filing. Certificates, plans, bailiff’s reports, translations and land registry copies also generate costs. The deposit of compensation by the expropriating authority is not a fee charged to the owner.

As for time limits, the administrative inquiry lasts two months, and the transferability order allows the matter to be referred to the court for two years. An application for annulment must, in principle, be filed within the sixty-day time limit under Article 23 of Law 41-90. An expert assessment may take several months. Compensation proceedings often take twelve to thirty-six months at first instance, and longer in the event of an appeal; this estimate based on 2025-2026 practice varies significantly according to the court, the number of rights holders and issues arising during the expert assessment.

The most costly mistakes are signing without an expert assessment, waiting for work to begin, confusing an application for annulment with a compensation claim, or submitting only property listings. The absence of a land title does not extinguish the right to compensation, but it requires ownership to be proved by other means and often delays payment. The lawyer checks publications, calculates deadlines, appoints an expert and prepares observations on the court expert’s report. Their involvement is particularly useful before any final release is signed or as soon as a procedural defect is discovered.

Need a Real Estate Law lawyer?

Browse verified profiles near you

Browse the directory

Frequently Asked Questions

How is expropriation compensation calculated in Morocco?
Article 24 of Law 7-81 requires compensation for loss that is current, certain and directly caused by the expropriation. The judge considers, in particular, comparable sales, zoning, access, utilities, buildings and the use of the property. Any increase in value created solely by the public project is excluded. A court-appointed valuation may be ordered, but the court is not bound by the amount proposed by the expert.
Can an amicable compensation offer be rejected?
Yes, the owner may reject the offer without losing the right to compensation. It is advisable to reply in writing, propose a reasoned amount and retain proof of receipt. Contrary to a widespread claim, Article 10 of Law 7-81 does not set a general thirty-day time limit for every amicable offer. The deadline stated in the notice and the status of the proceedings must be verified.
What remedies are available against expropriation in Morocco?
An action for annulment challenges the legality of the administrative act, whereas compensation proceedings concern the amount offered or awarded. In principle, the former must be brought within the sixty-day period provided for in Article 23 of Law 41-90. Compensation is argued before the Administrative Court in the expropriation proceedings and then, where applicable, before the Administrative Court of Appeal. Retrocession may also be requested subject to the conditions of Article 43 of Law 7-81.
How long does a declaration of public utility remain valid?
Law 7-81 does not establish a general ten-year duration comparable to certain foreign legal systems. Where the declaration does not identify the properties, they must be designated within the time limit provided for in Article 7. The act declaring the properties transferable then allows the matter to be brought before the court for two years, in accordance with Article 9. If that period expires without a court application, new proceedings may become necessary.
Who determines expropriation compensation in the event of disagreement?
The expropriating authority first makes an offer based on an administrative valuation. If no agreement is reached, the Administrative Court determines the compensation. It may appoint a court expert to assess the property and market comparables. However, the judge retains the final say and may depart from the report if it is incomplete or insufficiently reasoned.
What property may be expropriated in Morocco?
Land, houses, apartments, business premises and other immovable property may be expropriated, whether registered or unregistered. Certain rights in rem over immovable property, such as usufruct, may also be affected. Movable property is not transferred under Law 7-81, although its relocation may cause compensable loss. Property forming part of the public domain is governed by different rules.
How can a court expert’s report be challenged?
The owner may submit written observations identifying errors in surface area, zoning, dates or comparisons. The owner must provide genuinely comparable sales, plans, planning documents and evidence of any buildings or activities that were disregarded. A supplementary expert assessment or a second expert assessment may be requested from the court. The judge decides whether there are sufficient grounds to order it.
Can the State begin work before final compensation is awarded?
Early possession may be judicially authorised before the final award is determined, but it requires the payment or deposit of provisional compensation. Deposit is common when ownership or distribution among heirs is disputed. It does not constitute acceptance of the final amount. If there is no apparent decision, the owner must have the works officially recorded and immediately request the details of the legal instrument relied upon.
What can be done if the public project is never carried out?
Article 43 of Law 7-81 provides for a retrocession mechanism where the property has not been put to its stated use, subject to the statutory conditions and time limits. The former owner must establish the initial transfer and the absence of any actual allocation to that use. Restitution normally requires resolving the issue of the compensation previously received. Mere delay in carrying out the project is not always sufficient, which is why the legal instruments and the actual use of the land must be examined.
Can unregistered land be compensated after expropriation?
Yes, the absence of a land title does not automatically preclude compensation. However, the owner must prove their rights through adoul deeds, inheritance documents, administrative certificates and other admissible evidence. Disputes between heirs or neighbours often result in the compensation being deposited. Land registration or judicial clarification of the rights may be necessary to obtain payment.