Off-plan property sales in Morocco: legal framework in 2026

Morocco VEFA
A VEFA is the sale of a building to be constructed, the price of which is paid progressively before the final transfer of ownership.
VEFA Law 44-00
Law No. 44-00 introduced into the DOC the Moroccan rules applicable to the sale of buildings in a future state of completion.
VEFA Law 107-12
Law No. 107-12 reformed reservations, payments, guarantees and several stages of the VEFA process.
VEFA preliminary contract
The preliminary contract describes the property and sets the price, payment schedule, completion period and commitments preceding the final sale.
VEFA final contract
The final contract is concluded after completion and enables the buyer to be registered on the land title.
ANCFCC ownership certificate
The ownership certificate identifies the registered owner and any mortgages, seizures and other land charges.

An off-plan property sale in Morocco, known as a VEFA or purchase from plans, concerns a building that the seller undertakes to construct within a specified period. The buyer pays the price in instalments according to the progress of the works, then concludes the final sale after completion. The rules are set out in Articles 618-1 et seq. of the Dahir forming the Code of Obligations and Contracts, or DOC. They may apply to an apartment, villa, commercial premises or other property sold before its construction is complete.

The system was introduced by Law No. 44-00, promulgated by Dahir No. 1-02-309 of 3 October 2002. It was subsequently revised by Law No. 107-12, promulgated by Dahir No. 1-16-05 of 3 February 2016 and published in Official Gazette No. 6440 of 18 February 2016. This reform governs reservations, calls for funds and the seller’s guarantees in particular. In practical terms, an old contract template found online may be legally outdated.

A VEFA is not limited to a reservation form signed in a sales office. The transaction normally includes an optional reservation, a preliminary contract drawn up in the legally required form, supervised performance of the construction works, procurement of the administrative documents and the final contract. Where the property is registered, the ownership right must be recorded at the Land Registry. This registration is governed by the Dahir of 12 August 1913 on land registration, as amended in particular by Law No. 14-07.

Before paying a substantial sum, the buyer must check the land title, the owner’s identity, the building permit, the plans and the specifications. Any registered mortgages, seizures, provisional registrations or easements must also be identified. A company responsible for marketing the development is not necessarily the owner of the land or authorised to collect the price. A recent ownership certificate issued by the ANCFCC, supplemented by the seller’s corporate documents, addresses some of these checks.

The special VEFA rules operate in conjunction with other legislation. The DOC remains applicable to contractual obligations, non-performance and warranties against defects. Law No. 31-08 protects consumer buyers, particularly against unfair terms and misleading practices. The Code of Civil Procedure determines the competent court and urgent measures, while land law governs registration of ownership. The entire case should therefore not be assessed on the basis of a single isolated article.

VEFA preliminary contracts in Morocco: conditions and checks

Property developer’s identity
The contract must state the seller’s legal identity, commercial register details and the authority of the person signing it.
Description of the off-plan apartment
The unit, floor, approximate area, appurtenances and intended use of the property must be described precisely.
Final VEFA price
The price and payment dates must be recorded in writing without allowing the developer to modify them freely.
VEFA delivery date
The completion period must be workable and accompanied by sufficiently precise grounds for extension.
Developer’s specifications
The specifications describe the promised materials, equipment, common areas and finishes.
Plans appended to the contract
Signed or clearly identified plans serve as evidence of any discrepancy upon delivery.
Withdrawal from a VEFA reservation
The regulated reservation contract provides a statutory one-month withdrawal period under the conditions laid down by Law No. 107-12.

Article 618-3 of the DOC governs the form of the preliminary contract. It must be executed before a legally authorised professional, in the form prescribed by the legislation, and provide the required guarantees of a legally established date. A selection form, reservation request or receipt signed by a salesperson does not provide the same protection. In practice, the buyer should obtain the draft contract several days before signing so that the terms can be checked and the appendices compared with the promises made during marketing.

The document must identify the parties and the property unambiguously. It states the land title references, the location of the project, the building permit, the composition of the premises, their floor, approximate area and appurtenances. Any parking space, terrace, cellar or garden must appear with its exact legal status. Caution: merely referring to “available parking” in a brochure does not prove that the buyer is acquiring a privately owned unit or an exclusive right enforceable against the other co-owners.

The contract also specifies the price, payment schedule, completion period, conditions for concluding the final deed and the guarantee provided by the seller. The specifications describe the materials, utility networks, equipment, common areas and finishes. The approved plans and the plan of the premises must be appended or designated by an indisputable reference. Without this traceability, it becomes difficult to prove that a delivered partition, façade, item of equipment or area does not match what was promised.

The price cannot be increased by a unilateral decision of the developer. A price-adjustment clause must have a lawful basis, a comprehensible method and sufficiently precise limits. Articles 15 to 20 of Law No. 31-08 also make it possible to challenge an unfair term imposed on a consumer. The same caution applies to a clause allowing the seller to modify all plans, materials or deadlines solely according to its own constraints: a limited technical adjustment is not equivalent to the power to alter the subject matter of the sale freely.

The reservation contract remains separate from the preliminary contract. Law No. 107-12 provides for a one-month withdrawal period and a mechanism for depositing sums received. The provision is commonly reproduced under an additional article number placed after Article 618-3, but this numbering must be checked against the consolidated text of the Official Gazette or Adala before it is cited in any instrument. This precaution avoids turning a substantively correct rule into a formally incorrect reference.

Lawyers at your service

Real Estate Law lawyers in Morocco

Verified profiles, members of Moroccan bar associations — call or message them directly from their page

Jad Berrada
5 years of experience

Jad Berrada

JB Law Firm•Casablanca

A lawyer at the Barreau de Casablanca, Jad Berrada heads JB Law Firm, a practice dedicated to strategic legal advice in business law. For the past five years, he has been assisting companies, investors and individuals in securing their transactions, achieving compliance and managing their disputes, both in an advisory and a litigation capacity. Trilingual (French, Arabic, English), he holds consultations by videoconference. His practice covers business law in the broad sense: company law, contract law, employment law, consumer law, land law, liability law and business criminal law. He also handles arbitration and mediation matters, favouring alternative dispute resolution methods whenever possible. The author of several works devoted to the practice of business law — including "The 50 skills your business lawyer must necessarily possess" and "Techniques of legal reading and analysis" — he upholds one conviction: it is skills and strategy, more than knowledge of the texts alone, that make his clients win. Rigour, pragmatism and an understanding of business stakes guide the support he provides. The firm also handles labour law (contracts, employment tribunal litigation, for employees as well as employers), commercial litigation and debt recovery, intellectual and industrial property (trademarks, patents, counterfeiting), real estate law and commercial leases, as well as proceedings before the administrative courts.

Business LawReal Estate LawLabor Law+16
French · Arabic · English
Online booking · no slot in the next 14 daysBook by phone or WhatsApp.
IMAD CHAHBOUNI
19 years of experience

IMAD CHAHBOUNI

Cabinet Me. IMAD CHAHBOUNI•Tetouan

Me Imad Chahbouni, a lawyer at the Tetouan Bar, assists individuals, entrepreneurs and companies with legal advice and with the handling of their litigation. The firm practises in particular in real estate law, family law, business law, commercial law, employment law and contract law. Each case is the subject of careful analysis, with clear and confidential communication. The firm is located at Wilaya Center, in Tetouan. Consultations are offered at the office and by telephone. Discussions may take place in French, Arabic, Darija, Spanish or English. For an initial contact or an appointment request, please contact the firm by telephone, WhatsApp or email, briefly specifying the purpose of your request and your availability.

Immigration LawReal Estate LawFamily Law+23
French · Arabic · Spanish · +2
Direct contact only
Oussama Razine
6 years of experience

Oussama Razine

Cabinet Me. Oussama Razine•Casablanca

Mr. Oussama Razine, lawyer at the Casablanca Bar and Doctor of Business Law and Arbitration.

Business LawReal Estate LawTax Law+12
French · English · Arabic
Direct contact only

Payment of the VEFA price: stages, special account and tax

VEFA reservation deposit
The payment associated with the reservation is limited to 5% of the price under the payment schedule prescribed by the DOC.
Payment upon the preliminary contract
A 5% portion of the price is payable upon valid conclusion of the preliminary contract.
Developer’s call for funds
Each call for funds must correspond to an actual stage of construction and the authorised percentage.
Special VEFA reservation account
Funds paid upon reservation must be deposited into the special account required by Law No. 107-12.
Cash payment to the developer
A cash payment or payment into a personal account makes proof and recovery much more difficult.
Balance upon handover of the keys
The 20% balance is normally payable upon the final contract and handover of the keys.
Taxes on the purchase of a new apartment
VAT, registration duties and land registration fees depend on the property’s tax classification and the rules applicable in 2026.

Article 618-6 of the DOC prevents the developer from setting calls for funds freely. The schedule established by Law No. 107-12 includes 5% upon reservation, 5% upon conclusion of the preliminary contract and 10% upon commencement of the works. Three further instalments of 20% are linked to the progress of construction, followed by a 20% balance upon the final contract and handover of the keys. A seller therefore cannot demand 50% at the reservation stage merely because its sales form so provides.

Under the statutory schedule, the three 20% instalments correspond to distinct technical phases: completion of the foundations to the required level, completion of the structural works for the entire property development, then completion of the works together with the required administrative documents. The timetable must be adapted when marketing begins after certain stages, without allowing funds to be collected contrary to the legislation. Before paying, the buyer may request the corresponding technical certificate, dated photographs and access to the construction site subject to the safety conditions set by the developer.

Reservation payments are subject to the protective special-account mechanism created by Law No. 107-12. Rather than reproducing uncertain additional DOC numbering, the consolidated provision published by the SGG or Adala should be checked when drafting the contract. The buyer must request the account details, proof of payment and the repayment conditions. A special reservation account does not mean that all subsequent payments remain blocked with the notary until delivery.

Each payment must leave a banking record linking the payer, project, unit and instalment. A cash payment, a cheque without a detailed receipt or a transfer to the company’s director creates an obvious risk. For a Moroccan residing abroad, a power of attorney may authorise a representative to check supporting documents and construction progress, but it must clearly limit the representative’s payment powers. The mandate exempts neither the developer from complying with the payment schedule nor the bank from monitoring transactions falling within its regulatory obligations.

Tax must be calculated separately from the commercial price. The buyer should not assume that a uniform VAT rate of 10% applies to every VEFA: the treatment depends on the nature of the transaction and the 2026 General Tax Code. Certain social or subsidised housing developments are subject to specific conditions, particularly concerning price, use and the parties’ commitments. Registration duties, Land Registry fees, and the notary’s fees and disbursements require a written breakdown prepared before the final deed.

VEFA completion guarantee: verification and enforcement

Morocco VEFA completion guarantee
This guarantee must enable the project to be completed within the limits and under the conditions set out in writing by the guarantor.
VEFA repayment guarantee
This guarantee is intended to repay the sums paid when the prescribed conditions of non-performance are met.
Developer’s bank guarantee
The bank’s undertaking must be verified directly with the issuing institution using the project references.
Abandoned property construction site
The suspension of construction must be formally recorded and notified promptly before enforcing the guarantee.
Declaration of claim against the developer
A claim must be declared within the applicable period if insolvency proceedings are opened against the developer.
Morocco ten-year insurance
Ten-year insurance covers certain serious defects after the works but does not replace the VEFA financial guarantee.

Article 618-9 of the DOC requires the seller, after the preliminary contract, to provide a guarantee for completion of the works or a guarantee for repayment of the sums paid in the event of non-performance. The two mechanisms do not produce the same result. The completion guarantee must allow the project to continue in accordance with the undertaking given. The repayment guarantee is intended to refund payments where the transaction fails and its conditions are met. The developer’s own funds or a simple construction loan do not replace this protection.

The guarantee may be issued by a credit institution, insurance company or authorised body in accordance with the applicable legislation. The buyer must obtain a complete copy identifying the beneficiary, project, amounts covered, duration, exclusions and triggering events. The buyer must then contact the issuer using official contact details independent of those provided by the salesperson. A letter merely stating that a bank is financing the developer does not necessarily constitute an undertaking that buyers can enforce.

Ten-year liability insurance must also be distinguished from the VEFA guarantee. It applies after the works to certain serious damage falling within the builders’ liability, subject to the policy and lawful exclusions. By its nature, it is not intended to finance completion of an abandoned construction site. The buyer must therefore separately check the financial guarantee, construction-site insurance and ten-year cover. A certificate without a policy number, duration, insured project or precise identity of the policyholder is insufficient to assess the actual protection.

When construction stops, evidence must be gathered immediately: the contract, payment schedule, receipts, calls for funds, photographs, correspondence and a copy of the guarantee. A court enforcement officer may formally record the apparent condition of the construction site without determining technical liability. A formal notice is then sent to the seller, and the claim submitted to the guarantor must strictly comply with the guarantee issued. A bank guarantee is construed literally: an incorrect project designation, a missing document or a late claim may prevent its enforcement.

If several buyers are affected, they may share certain information or the cost of a formal report, but each retains their own contractual rights and amounts. If the developer becomes subject to safeguard, judicial reorganisation or liquidation proceedings, the claim must be declared within the period set by the Commercial Code and the publication of the decision. Waiting for the outcome of a property expert assessment may then be dangerous. The guarantee, the claim against the seller and any land rights must be examined separately.

Developer delivery delay: procedure and compensation

Developer delivery delay in Morocco
The delay is assessed from the contractual deadline after reviewing the grounds invoked for extending it.
Formal notice to developer
The formal notice describes the delay, recalls the payments made and requires performance within the applicable period.
VEFA delay penalty
Article 618-12 provides for 1% per month on the relevant basis, subject to an overall cap of 10% and its applicable conditions.
Bailiff’s report on construction site
The report provides a factual description of the apparent condition of the construction site without determining the developer’s liability.
Court-ordered VEFA expert assessment
The court-ordered expert assessment evaluates progress, non-compliance and the foreseeable cost of the works.
Termination of VEFA contract
Termination may be sought when the delay or abandonment constitutes a sufficiently serious breach.

The delay is calculated from the contractual completion or delivery deadline, after reviewing the extension clauses. Adverse weather, an administrative decision or a supply difficulty does not automatically constitute force majeure. The developer must establish the event, its external or unforeseeable nature depending on the legal classification invoked, and its actual effect on the schedule. A clause allowing an unlimited extension without verifiable justification may be challenged under Article 230 of the DOC, the requirement of good-faith performance and Law No. 31-08.

The first step is to gather the contract and supporting documents, then have a precise formal notice served. It recalls the property, the missed deadline, the amounts paid, the apparent condition of the works and the obligation whose performance is required. Service by a bailiff provides strong evidence of the date and content. The VEFA regime makes certain remedies contingent on a formal notice remaining unsuccessful for sixty days. This period must not be confused with a thirty-day commercial period sometimes included in contracts.

Article 618-12 of the DOC, as amended by Law No. 107-12 published in Official Bulletin No. 6440 of 18 February 2016, provides for compensation of 1% per month, capped at 10%. Where the seller is in delay, the basis consists of the amounts paid by the buyer; where the buyer is in default, the text refers to the due and unpaid amounts. The calculation requires the statutory conditions, including the formal notice and the applicable period, to be met. A clause cannot be interpreted outside this chronology.

If the condition of the construction site is disputed, an application may be made to the president of the court to order an expert assessment or an inspection measure. Articles 148 and 149 of the Code of Civil Procedure govern ex parte orders and summary proceedings respectively. The expert may assess progress, outstanding works and certain technical instances of non-compliance, but does not order termination or determine liability. The report provides the court hearing the merits with the information needed to assess the seriousness of the delay and quantify the works.

Proceedings on the merits may seek performance, penalties, damages or termination. Rent, loan interest, travel expenses or loss of use must be substantiated and linked to the delay. For 2025-2026, the ranges observed in practice are approximately 800 to 2,500 DH for a bailiff’s report and 5,000 to 20,000 DH for the advance deposit required for a court-ordered expert assessment. These indicative estimates vary according to the city, the number of units, travel and the scope of the assignment set by the court.

Non-compliant apartment: reservations and warranties

Reservations upon handover of keys
Visible defects must be described precisely in the delivery report before it is signed.
Apartment not compliant with plans
Non-compliance is proved by comparing the delivered property with the contractual plans and specifications.
Latent defect in new apartment
A latent defect is a defect that is not normally detectable and affects the use or value of the property.
DOC warranty for property defects
Articles 549 to 574 of the DOC govern the warranty against defects, with the time limit for immovable property provided by Article 572.
Ten-year warranty in Morocco
Article 769 of the DOC covers certain serious defects attributable to the specified builders for ten years.
One-year warranty for equipment
Article 769, paragraph 2, provides within its scope one-year protection for certain equipment separable from the structure.
Reduction in property price
A reduction in price requires proof of the non-compliance and the resulting loss in value.

Upon handover of the keys, the buyer must compare the dwelling with the contract, plans and specifications. The buyer checks the surface area, partitions, openings, parking space, finishes, connections, equipment and accessible common areas. Visible differences are recorded in a dated report, with a usable description and, if possible, photographs. If the seller refuses to include the reservations, they may be notified immediately by a bailiff. An oral promise to repair does not replace a written reservation.

Articles 549 to 574 of the DOC govern the warranty against defects in the item sold. For immovable property, the special time limit for bringing an action must be sought in Article 572, not Article 573, which concerns the sale of animals. Subject to its conditions and the legal grounds for interruption or suspension, Article 572 establishes a one-year period after delivery for actions relating to defects in immovable property. The special provisions of Articles 618-1 et seq. and the valid VEFA terms must also be examined.

An apparent defect could have been detected through a normally diligent inspection upon delivery. A latent defect was not reasonably detectable and affects the use or value of the dwelling. This distinction determines the evidence, notices and remedies. Upon discovering water ingress, a crack or a network defect, the buyer must preserve photographs, obtain a diagnostic assessment and notify the seller. Waiting several months may facilitate a dispute over the discovery date, maintenance of the property or aggravation of the damage.

Article 769 of the DOC establishes the ten-year liability of the architect, engineer and contractor, according to their respective assignments, for serious defects affecting the structural integrity or intended use of the building. Paragraph 2 also provides, within its scope, a one-year warranty for certain equipment separable from the structure. It is therefore incorrect to state that such equipment is protected only by a contractual warranty. However, there is no general two-year warranty identical to the French regime: the classification of the construction project, equipment and damage remains decisive.

The ten-year period is linked to acceptance of the works, but Article 769 also requires prompt action after the damage becomes apparent. According to the prevailing case law of the Moroccan Court of Cassation, the short period for bringing an action runs from the actual discovery of the damage giving rise to the warranty, not automatically from acceptance. The Court of Cassation’s public database is cited in support of this position; no unverified judgment number is reproduced here. In practice, an immediate expert assessment and consultation help avoid a dispute over admissibility.

Depending on the seriousness, the buyer may request compliance, the cost of the works, a reduction in price, damages or termination. For 2025-2026, a private expert assessment often costs 2,000 to 10,000 DH, while a complex court-ordered expert assessment may require an advance deposit of 5,000 to more than 20,000 DH. These ranges observed in practice remain indicative. The court sets the amount according to the assignment, the number of dwellings, the technical specialisations and the expert’s travel.

VEFA termination, competent court, costs and timeframes

Canceling a VEFA in Morocco
Except for withdrawal from a reservation, ending the contract requires a written agreement or legal grounds for termination.
Refund of deposit by developer
The refund depends on the established breach, the available guarantee and the seller’s solvency.
Court for property developer disputes
The Court of First Instance generally has jurisdiction over a dispute involving an individual buyer.
Property summary proceedings in Morocco
The summary proceedings judge may order an expert assessment or interim measure without finally terminating the contract.
Pre-registration on land title
Pre-registration temporarily protects a property claim if the land registration and procedural conditions are met.
Lawyer’s fees for VEFA dispute
In 2025-2026, first-instance fees observed in practice often range from 8,000 to 30,000 DH excluding taxes.

An amicable termination is possible if the parties agree in writing on ending the contract, returning the payments, penalties and the status of land registry entries. The settlement agreement must set a payment date and avoid a general waiver before the funds are actually received. In the absence of an agreement, Articles 230, 259 et seq. of the DOC allow judicial termination of a synallagmatic contract to be sought for a sufficiently serious breach. The judge assesses the delay, abandonment of the construction site, payments made and realistic prospects of completion.

Obtaining a judgment ordering repayment and actually recovering the amount are two different matters. The financial guarantee, attachable accounts and the seller’s assets must be checked. For registered immovable property, a pre-registration may temporarily preserve a claim under the conditions of the Dahir of 12 August 1913. A protective attachment may also be sought where a claim appears well founded and its recovery is at risk. Caution: a disproportionate or unfounded measure may incur the applicant’s liability.

Article 18 of the Code of Civil Procedure contributes to determining the subject-matter jurisdiction of the Court of First Instance; it must not be presented merely as a rule of jurisdiction based on the value of the claim. Territorial jurisdiction then depends on Articles 27 and 28 and the nature of the action. An action in rem relating to immovable property is in principle connected to the location of the property, while a contractual claim requires precise legal classification. For a consumer buyer, the Court of First Instance is generally petitioned, subject to any specifically assigned jurisdiction.

The president of the court may intervene in summary proceedings to order an expert assessment, inspection or protective measure, without ordering termination on the merits. The judgment may then be appealed, followed by an appeal to the Court of Cassation limited to reviewing questions of law. First-instance proceedings involving an expert assessment often take 12 to 24 months and may take 18 to 36 months in a complex case. An appeal may add approximately 18 to 36 months. These are timeframes observed in practice in 2025-2026, not timeframes guaranteed by the courts.

Lawyer’s fees are agreed with the client according to the complexity, amount at stake and work required. For 2025-2026, an indicative range of 8,000 to 30,000 DH excluding taxes is often observed at first instance, with higher amounts where several buyers, experts or protective measures are involved. Bailiff, expert, translation and land registry costs, as well as applicable court fees, must be added. The fee agreement must distinguish fees, disbursements, appeal and enforcement. Legal aid remains available subject to the statutory means requirements.

VEFA limitation periods, common errors and lawyer’s role

Limitation period for developer disputes
The applicable period may be fifteen years, five years, one year or a special short period depending on the action brought.
Limitation period for ten-year warranty in Morocco
The ten-year period and the short period following discovery of the damage must be distinguished under Article 769 of the DOC.
Property reservation form
A commercial document does not replace the regulated contract and must be reviewed before any payment.
Guarantee cheque for developer
A cheque provided outside the payment schedule may circumvent statutory protections and complicate proof of payment.
Refusal to accept keys
The refusal must be based on sufficiently serious defects and supported by dated evidence.
Power of attorney for MRE property purchase
The power of attorney must specify the authorised acts and comply with the formalities of the country where it is signed.
VEFA property lawyer
The lawyer reviews the contract, preserves the applicable time limits and directs the remedy against the seller, guarantor or relevant builders.

There is no single limitation period for all VEFA disputes. Article 387 of the DOC establishes a general limitation period of fifteen years where no special provision applies. Article 5 of the Commercial Code provides for five years for obligations arising in connection with commercial activities between traders or between traders and non-traders, subject to the legal classifications adopted. Actions under the warranty against defects in immovable property are governed in particular by Article 572, while Article 769 contains its own time limits. Each claim must therefore be dated and legally classified separately.

For ten-year liability, the ten-year period attached to the structure must be distinguished from the short period for bringing an action after discovery of the harmful event. Prevailing Moroccan case law links the starting point of this second period to the actual discovery of the defect. A formal notice does not necessarily interrupt every time limit in the same manner as a court claim. The contract, the debtor’s acknowledgment, the expert assessment and the summons must be analysed in light of the relevant period, without mechanically applying the rules governing another action.

A common error is to sign a summary reservation form and then make a payment on the salesperson’s oral instructions. Another is to accept post-dated cheques or payments outside the payment schedule. Paying the balance before the final deed, administrative documents and keys are provided also places the buyer in an unfavourable bargaining position. In practical terms, every amount must correspond to a statutory stage, a reviewed clause and a banking record. It is generally easier to challenge an irregular payment request than to recover an advance payment.

Upon delivery, signing the words “without reservations” based on a promise of prompt repairs weakens the case. Every visible defect must be recorded in writing, photographed and accompanied by a dated request. Conversely, refusing all keys because of a minor imperfection may be classified as unjustified conduct and trigger a claim for payment. The strategy depends on whether the dwelling can be occupied, the cost of repairs and the seriousness of the discrepancy. A jointly attended inspection or an expert assessment often helps move beyond a purely verbal dispute.

For an MRE, the power of attorney must specify whether the attorney-in-fact may visit the construction site, receive a formal notice, pay an instalment, sign a report with reservations or appoint an expert. When executed abroad, apostille, legalisation or consular formality requirements depend on the country of signature and the applicable conventions. A translation by a sworn translator may be required in Morocco. An overly broad general power of attorney may authorise acts that the buyer did not genuinely intend.

A lawyer may intervene before litigation to review the land title, the selling company, the guarantee, the contract and the payment schedule. After an incident, the lawyer identifies the liable parties, preserves evidence and chooses between negotiation, an expert assessment, a protective measure, performance or termination. Above all, the lawyer checks the specific time limits for each legal basis, because a legally valid claim may become inadmissible if brought late. The lawyer’s involvement guarantees neither completion nor repayment, but reduces the risk of proceedings being brought against the wrong party or on an unsuitable legal basis.

Need a Real Estate Law lawyer?

Browse verified profiles near you

Browse the directory

Frequently Asked Questions

What rights does a buyer have in an off-plan sale in Morocco?
The buyer benefits from the regime established by Articles 618-1 et seq. of the Code of Obligations and Contracts, as amended by Law No. 107-12. The buyer may require a compliant contract, a payment schedule linked to the progress of the works, a financial guarantee, and delivery in accordance with the plans and specifications. In the event of non-performance, the buyer may seek performance, compensation, or termination, depending on the seriousness of the breach and the evidence gathered.
What must a preliminary off-plan sale agreement contain in Morocco?
The agreement must identify the seller, the land, the land title, the building permit, and the property sold. It must specify the price, payment schedule, completion deadline, conditions of the final sale, and the guarantee provided by the developer. The plans, specifications, and technical documents must be appended or identified unambiguously.
Can a buyer withdraw after reserving an off-plan apartment?
Law No. 107-12 provides for a one-month withdrawal period for a regulated reservation agreement, as well as the reimbursement of amounts paid under the conditions prescribed by law. This rule appears in the provisions added to the COC following Article 618-3; the numbering should be checked against the official consolidated version before being reproduced in a legal instrument. After the preliminary agreement, there is no general right to withdraw without cause.
What should be done if the developer delays delivery?
The contractual date should be compared with the actual progress of the works, after which the developer should be served with a formal notice bearing a legally established date. Subject to its conditions, Article 618-12 of the COC provides for compensation of 1% per month, calculated on the relevant amounts and capped at 10%, after the statutory period following the formal notice. An expert assessment in summary proceedings may establish the condition of the construction site before a claim for performance, compensation, or termination is filed.
How does the completion guarantee work for off-plan sales in Morocco?
Article 618-9 of the COC requires a completion guarantee or refund guarantee after the preliminary agreement. The buyer must obtain the complete guarantee instrument and verify its authenticity with the bank, insurer, or issuing entity. If construction stops, the claim submitted to the guarantor must strictly comply with the events, documents, and time limits specified in that instrument.
Can the developer change the price or plans?
The developer may not freely change the agreed price, surface area, or specifications. A substantial change requires a lawful contractual basis and, where it changes the subject matter of the sale, the buyer’s written consent. A clause granting the seller unlimited power to make changes may be challenged under the COC and Articles 15 to 20 of Law No. 31-08 concerning unfair terms.
How should an off-plan apartment in Morocco be paid for?
Payments must comply with Article 618-6 of the COC and correspond to the actual progress of the works. The statutory schedule notably includes 5% upon reservation, 5% upon signing the preliminary agreement, 10% upon commencement of the works, three instalments of 20% linked to construction progress, and then 20% upon signing the final agreement and handing over the keys. Each payment must be traceable and made to the legally designated account, never to a manager’s personal account.
What compensation can be claimed for a non-compliant apartment?
The buyer may seek repairs, compliance with the agreed specifications, a price reduction, or damages corresponding to proven loss. Termination may be considered if the non-compliance is sufficiently serious. The delivery report, contractual plans, specifications, photographs, and expert assessment may be used to establish the defect and its cost.
Which court should hear a claim against a property developer in Morocco?
A claim by an individual buyer generally falls within the jurisdiction of the Court of First Instance, with territorial jurisdiction assessed according to whether the claim concerns the property or the contract. The President of the Court may hear an application in summary proceedings for an expert assessment or a protective measure. The Commercial Court may have jurisdiction in certain professional or commercial circumstances, which must be verified before proceedings are initiated.
What VAT and taxes apply to an off-plan sale in Morocco?
The purchase is not automatically subject to 10% VAT. The applicable regime depends on the classification of the property, the transaction carried out, and the provisions of the General Tax Code in force in 2026; certain social housing programmes receive special treatment subject to strict conditions. Registration duties, land registration fees, professional fees, and any housing assistance must be calculated separately with the notary and, if necessary, the General Tax Directorate (DGI).

Have your off-plan purchase file reviewed

Before making a payment, accepting the keys, or bringing a claim against the developer, consult a real estate lawyer on AvocatLib to review the agreement, guarantees, and available evidence.

Consult a real estate lawyer